New power unit No. 11

Works realised in 2015:

  • Assembly of the boiler house's main structure
  • Assembly of the machine room’s housing
  • Assembly of a stator and rotor of the generator
  • Assembly of cooling water pumps
  • Assembly of start-up boilers
  • Assembly of unit, tap and reserve transformers
  • Assembly of electrostatic precipitator's supporting structure
  • Performance of reinforced concrete structures of ash tanks
  • Performance of reinforced concrete structure of gypsum store

Works planned in 2016:

  • Connecting the voltage of 110 kV and 400 kV
  • Assembly of the pressure system - water test of the boiler
  • Rinsing - etching of the boiler
  • Start-up of the starting boiler house
  • Boiler start-up
  • Assembly of stacker-reclaimers
  • Assembly of coal pulvilizers
  • Start-up of the whole power plant

A new 1,075 MWe unit in Kozienice Power Plant

  • The largest in Europe power unit fired with bituminous coal
  • Completely independent unit, possessing its own infrastructure
  • New unit means a 1/3 increase in the Kozienice Power Plant's capacity
  • Unit No. 11 will allow to eliminate deficits of energy on the market
  • High efficiency of energy generation
  • High availability and low failure rate of the new unit
  • The unit satisfies the conditions of the environmental protection

Due to the modern technology used by the construction of the new unit in Kozienice Power Plant there is a reduced CO2 emission.